Thames Water announces next stages of market engagement for development of South East’s reservoir

  • Thames Water announces next stages of market engagement for development of South East’s reservoir
    Thames Water - SESRO - View of Oxfordshire reservoir from North.
  • Thames Water has today published a Periodic Indicative Notice (PIN) to initiate early market engagement for its proposed reservoir in Oxfordshire.   
  • The reservoir, also known as the South East Strategic Reservoir Option (SESRO), is crucial to securing future water supply for 15 million Thames Water, Southern Water and Affinity Water customers.   
  • The notice signals the next stage in the company’s market engagement programme for the reservoir and Thames Water is encouraging interested parties to register their interest in participating. 

About the entity

Thames Water
Every day, we serve 15 million customers across London and the Thames Valley.

Thames Water has today (Tuesday 7 January 2025) issued a Periodic Indicative Notice (PIN) to inform potential suppliers and investors about the next stage of its market engagement programme which will support the development of a new reservoir in Oxfordshire.   

With a capacity of up to 150 million cubic meters and a surface area of approximately 7 square kilometres, the proposed reservoir is set to become a key regional asset, supplying 15 million people across the region. The reservoir has also been designated a Nationally Significant Infrastructure Project, with the government recently approving the company’s Water Resource Management Plan 2024, including the needs case for this major asset.    

The reservoir is expected to be operational by 2040 and will support Thames Water, Southern Water and Affinity Water in delivering a safe and secure supply of water during periods of drought. It will also help to meet the increasing pressures of climate change and demands of a growing population.   

Early market engagement 

Thames Water’s early market engagement aims to update contractors and investors on the development of the reservoir, including the company’s commercial and procurement strategies for two large scale future opportunities:  

  • Infrastructure Provider (IP): The IP will be responsible for taking forward the design, building, and financing the majority of assets within the SESRO project. 
  • Main Works Contractor (MWC): To construct and commission the assets under a target price contract, working initially with TW and then the IP once the IP contract is awarded. 

In addition, the engagement is also an opportunity to shape the market and encourage cross-party conversations that align the project to market trends, taking into account both contractor and investor perspectives.  

Mohit Farmah, Head of Procurement and Supply Chain at Thames Water, said: "We are excited to kick-start the year by getting the next stage of market engagement for our proposed reservoir underway.  

 “Contractors and investors have a crucial role to play in informing our approach and helping drive this vital project forward. We have been encouraged by the level of interest the market has shown to date.  

 “I encourage all interested parties to register their interest to engage with us and shape the future of this vital project, including our spring market engagement event on Monday 17 March”.  

Participation and next steps   

Interested organisations are invited to register their interest in the market engagement by completing the registration-of-interest form. Registration for the SESRO spring market engagement event taking place on Monday 17 March 2025, will close on the Friday 24 January 2025. 

Should you have questions please contact Thames Water’s market engagement team at marketengagement.sesro@thameswater.co.uk  

Subscribe to our newsletter

Topics of interest

The data provided will be treated by iAgua Conocimiento, SL for the purpose of sending emails with updated information and occasionally on products and / or services of interest. For this we need you to check the following box to grant your consent. Remember that at any time you can exercise your rights of access, rectification and elimination of this data. You can consult all the additional and detailed information about Data Protection.