NWC could issue Narjis sewerage tender early next year

Saudi Arabia’s National Water Company (NWC) could announce the construction tender for its Narjis project in the first quarter of 2022. The $250 million plan includes the construction of the main lines, lifting station and sewerage networks in the Narjis district in Riyadh region.

According to ZAWYA, a source close to the project said: “The prequalification submission deadline was 29 November 2021. The tender for the main construction is expected to be released by early March 2022.”

The estimated cost of the project is $250 million and is to be completed by the first quarter of 2026. The company or consortium awarded the project involves the construction, installation and execution of a sewage lifting station with a design capacity of 55,000 cubic metres/day, main lines with a length of approximately 16 kilometres, with diameters from 400-1000 mm, in addition to the implementation of 265-km of sewage networks north and south of King Salman Road. 