USBR awards $46m construction contract to build two pumping plants in New Mexico

  • USBR awards $46m construction contract to build two pumping plants in New Mexico

About the entity

Bureau of Reclamation
Reclamation is the largest wholesale water supplier in the United States, and the nation's second largest producer of hydroelectric power. Its facilities also provide substantial flood control, recreation, and fish and wildlife benefits.

The Trump Administration is building facilities that will provide secure clean and reliable water to the Navajo Nation and rural communities in northwestern New Mexico.

In order to meet this goal, the Bureau of Reclamation awarded $45,945,150 to Archer Western Construction, LLC of Phoenix, Arizona to construct the Tooh Haltsooi Pumping Plant (Pumping Plant Number 4) near the community of Sheep Springs, New Mexico and Bahastl’ah Pumping Plant (Pumping Plant Number 7) near the communities of Twin Lakes and Coyote Canyon, New Mexico.

“Today, we take another step to provide clean, reliable water supplies to the Navajo Nation and the other project participants in rural communities,” said Commissioner Brenda Burman. “These pumping plants will help deliver water from the San Juan River to communities along the San Juan Lateral pipeline.”

The Navajo-Gallup Water Supply Project will provide a long-term, reliable water supply for 43 chapters on the Navajo Reservation, the southwest area of the Jicarilla Apache Reservation, and the City of Gallup, New Mexico, which is a 7,814 square mile service area - roughly the size of New Jersey. When completed, it will include approximately 300 miles of pipeline, two water treatment plants, 19 pumping plants, and multiple water storage tanks.

The plants are just two of several pumping plants associated with the project and will help convey water through the project pipeline from the San Juan River to Navajo communities and the City of Gallup.

Under this contract, construction will include installation of canned vertical turbine pumps and associated electrical and mechanical equipment, yard piping, and a water treatment building at the Tooh Haltsooi Pumping Plant site. Each will have four equally sized pump and motor units with a total capacity of approximately 47.7 cubic feet per second at Tooh Haltsooi Pumping Plant and 40.4 cfs at Bahastl’ah Pumping Plant. In addition, a million-gallon water storage tank will be constructed at Tooh Haltsooi Pumping Plant and a 1.5-million-gallon water storage tank will be installed at Bahastl’ah Pumping Plant.

Construction of the two plants is expected to take up to three years, and when completed, each plant and associated structures will occupy just over two acres within a fenced area.

Subscribe to our newsletter

Topics of interest

The data provided will be treated by iAgua Conocimiento, SL for the purpose of sending emails with updated information and occasionally on products and / or services of interest. For this we need you to check the following box to grant your consent. Remember that at any time you can exercise your rights of access, rectification and elimination of this data. You can consult all the additional and detailed information about Data Protection.